Electricity consumers in Gombe and some parts of Yola and Bauchi States will experience power outage as a result of scheduled maintenance of power facilities by the Transmission Company of Nigeria.
The TCN announced that its maintenance crew will carry out scheduled preventive maintenance on the bay of its T1A 150MVA, 330/132/33kV transformer bay.
According to a statement by the TCN General Manager, Public Affairs, Ndidi Mbah, the maintenance will last for some hours and to commence the maintenance exercise, TCN would transfer the load from T1A 150MVA transformer to its T2A 150MVA transformer in the same substation.